Infrastrata PLC – Islandmagee Gas Storage Project Update

InfraStrata plc (AIM: INFA), the UK quoted company focused on boosting national energy resilience with strategic infrastructure projects, is pleased to provide an update on the workstreams completed at the Islandmagee gas storage project (“Islandmagee Project” or “the Project”) in Northern Ireland.   

 

The process to convert the draft marine licence to a full marine licence is progressing on schedule and the Board continues its close discussions with the Department for Agriculture, Environment and Rural Affairs in Northern Ireland (DAERA).  In addition, the pre-construction marine baseline field work is now complete. Early indications are that the results are in line with, or better than, the previous data gathered.

 

Following completion of the workstreams listed below in the past two months, the Islandmagee Project is in the final phase of pre-construction activities. Negotiations with the Company’s chosen equity partner are in the advanced stage and all being well, are expected to be completed as part of taking FID.

 

Description

Status

Engineering

Value Engineering

√ – Completed

Land

All easements acquired

√ – Completed

All key land areas acquired

√ – Completed

Environmental

Shadow Habitats Assessment

√ – Completed

Updated Brine Model

√ – Completed

Independent Verification of Brine Model

√ – Completed

Environmental Monitoring plan

√ – Completed

Pre-Construction

Field work – 28-day tidal monitoring

√ – Completed

Field Work – Seabed video monitoring

√ – Completed

Field Work – Grab Sampling

√ – Completed

Field Work – Scientific Beam Trawling

√ – Completed

Field Work – Bird Monitoring (Vessel)

√ – Completed

 

2019 Remaining Milestones

 

Description

Completion target

Pre-Construction

Report – Final tidal report

September

Report – Final Seabed monitoring report

September

Report – Final Grab Sampling

September

Report – Final Scientific Beam Trawl

September

Report – Final Bird Monitoring

September

Draft Marine Baseline Report & updated Environmental Impact Assessment

September

Secure all sites and terminate temporary use agreements

September

Final Marine Baseline Report & Environmental Impact Assessment Issued to DAERA

October

Submission of planning pre-construction documentation

November

Environmental

Notification of public consultation dates

Q4’19

All reports made available on the Islandmagee Energy Website

Q4’19

Venues and dates of Islandmagee Energy public information sessions for public consultation made available on the website

Q4’19

Corporate

Issue of draft Gas Storage Agreement

September

Final payment against EU Reclaim for completed FEED works

Q4’19

Release of revised construction tender documents

October

Appointment of Chairman

Q4’19

Heads of Terms agreed for project equity funding

Q4’19

Equity funding agreement executed

Q4’19

Commencement of enabling works prior to full scale construction

December

Final Investment Decision (FID)

December

 

During this time, the Company has maintained an open dialogue with the local community and management is pleased with the volume of support the Project is attracting locally. InfraStrata appreciates that local residents must have confidence in the design and environmental management of the Project. Therefore, management is committed to delivering the highest levels of regulatory compliance and is engaged in regular consultation with residents to ensure they have that reassurance.

 

John Wood, CEO of InfraStrata, said, 

 

“Our work is progressing at pace. As we have set out today, we have a defined plan to deliver the workstreams required by the end of the year in order to make the Final Investment Decision and to commence construction in 2020. Having followed due process, we are confident that we will receive the marine licence, which will represent a key project milestone. We are committed to developing it in a way which benefits the local communities and environment in which we operate. When delivered, this project will dramatically enhance the UK’s energy resilience.”

infrastrata

Share the Post:

Other News

Infrastrata PLC – Interim Results

InfraStrata plc (AIM: INFA), the UK quoted company focused on strategic infrastructure projects and physical asset life-cycle management, is pleased to present its unaudited interim results for the six-month period ended 31 January 2020.

Read More

Infrastrata PLC – Strategy Update

InfraStrata plc (AIM: INFA), the UK quoted company focused on the development of natural gas storage capacity, is pleased to provide an update and confirmation of its wider strategy to seek to become revenue generating during 2020 after taking Final Investment Decision for the Islandmagee Gas Storage Project.

Read More

RISK WARNING